South Station Bus Terminal

South Station Bus Terminal in Boston, MA
Building: South Station Bus Terminal
Client: Newmark Knight Frank
Location: Boston, Massachusetts
Type: Historic Bus Station
Project Overview: In 2005, Stuart Dean was contracted by the South Station Bus Terminal’s management firm, The Codman Company, to perform a one-time restoration of the building’s façade. Years of train exhaust had formed severe diesel deposits on fascia panels directly above train tracks. Though the panels had been treated with high-performance coating, they were past due for a major cleaning.
Challenge: The South Station Bus Terminal operates nearly twenty-four hours a day, seven days a week. So as not to interfere with the building’s bustling schedule, Stuart Dean’s façade restoration technicians cleaned the panels by working above the adjacent train tracks between midnight and 5:00AM.
Work Completed: Clean with 100% cotton towels and Simple Green. We were to recapture all effluent. No rundown was to drip off the wall panels and contact the tracks below. This was a basic cleaning job. The trick was in the access (Safeworks set up a special davit system and we worked off their supplied rigging between the hours of Midnight and 4 a.m. Work was done in less than 2 working weeks. There were about 5 or 6 drops and we had 3 or 4 mechanics on the staging.
Results: The black soot buildup was completely removed, eliminating an eyesore familiar to millions of Boston commuters. Stuart Dean has already been asked to perform a follow-up cleaning.
Client Feedback: Stuart Dean refinished our soot and grime plagued Alpolic fascia panels above the railroad tracks leading into South Station. Not only was the before and after difference dramatic, but the job was completed safely and ahead of schedule. The Stuart Dean mechanics worked at odd hours, in a difficult environment and exceeded my expectations! Their planning, supervision and execution was flawless.

Thanks for making a difference. I would recommend Stuart Dean without reservations. Stephen Squibb, General Manager

For more information on this project and others completed in New England, please contact Peter Seoane, Division Manager, 617-464-7201, pseoane@stuartdean.com.